The Disposition and Development Agreement (DDA) has been released regarding the purchase of the Daughtrey’s building from the County which purchased it in 2011. The building has not had a permanent tenant in over ten years. The DDA is comprehensive in its scope, but has some very definite time deadlines. These are all spelled out in detail in “Exhibit C,” the Schedule of Performance with a series of “no later than” dates.
If all of these dates are extended to the maximum allowable time, we see that the scope of this project could drag out for more than seven years.
The DDA is set to be voted on by the Alameda County Board of Supervisors on June 24th. Assuming that the deal is approved, here are some highlights from the Schedule of Performance, illustrating how excruciatingly long this redevelopment could be.
Highlights:
That means the County and Purchaser have until December 31, 2015 to satisfy all the pre-deal requirements the DDA talks about.
This means the Developer potentially does not need to pay any money out on the deal for one and a half years.
That means the County does not have to start the construction on the new shared parking plan for almost two years. The multiple blighted and ineffectual lots could remain as-is until then
This means the developer does not need to obtain and finalize commitments from his secondary tenants for two and a half years.
This means the fancy new shared parking lot behind the Daughtrey’s building, Ice Creamery, and Fong’s does not potentially need to be completed for two and a half years.
This means that the actual closing on the sale of the property could potentially not happen for five and a half years.
This means that the final reconstruction of the building and surrounding property (and thus the end of the ongoing blight,) does not potentially need to be completed for a little more than seven years.
In summary, from the date that the Board of Supervisors is set to approve the DDA, June 24, 2014 to the final potential date of completion is 2655 days, or seven years, three months and six days.